Facilities Design and Construction
-
Facilities Design & Construction (FD&C) services focuses on the design and management of construction, remodeling and renovation projects for all of Marietta City Schools’ educational and support facilities.
We are committed to the design and construction of safe, sustainable and energy efficient facilities that enrich the creative learning and teaching environment for our students and staff!
Key Projects
-
College & Career Academy Project - Phase I (in progress)
This project is Phase I of II in the construction transformation of Marietta High School: A Georgia College and Career Academy. This new addition is built on a flexible and adapatble construction design allowing for feasible improvements and modifications to the layout of the building.
- Groundbreaking: July 26th, 2018
- Soft Opening Target – January 2020
- Hard Opening Target – August 2020
- Approximately 50,000 square feet (Tri-Level)
- New learning spaces include:
- Engineering, Drawing, and Design Laboratory
- Architecture & Design Laboratory
- Construction Technology Laboratory
- Engineering Technology Laboratory
- STEM Gym – combined Construction Tech and Engineering Tech labs offering approximately 4,000 sq. ft. of production space
- Cybersecurity Lab
- Gaming Design Lab
- Business Laboratory
- College & Career Advisory
- Post-secondary Learning Lab
- four general purpose classrooms
- Atrium (Square) - Common Learning Spaces…based on the Greek Agora to function as “a marketplace of ideas”
- Patio (Porch) - Outdoor mentoring/reflection space…based on the Greek Stoa to function as “a place for collaboration” Administrative space
- “Coffee Bar”
- Faculty Workroom
- Conference Room
Gallery
-
College & Career Academy Project - Phase II (coming late 2019)
This project is Phase I of II in the construction transformation of Marietta High School: A Georgia College and Career Academy. This project includes a repurpose of selected exisiting space in the main building to create additional learning labs for college and career advancement.
- Work timeline: January 2020
- Hard Opening Target – August 2020
- Approximately 32,000 square feet
- New learning spaces include:
- Healthcare Laboratory
- Sports Medicine
- Emergency Services
- Nursing
- two additional classrooms
- Biotechnology Laboratory
- Audio-Visual Technology Film Studio
- Early Childhood Learning Laboratory
- Information Technology Laboratory
- Culinary Arts Laboratory
- expansion of current kitchen to include an additional prep kitchen and dining room
- three general purpose classrooms
- Healthcare Laboratory
-
Park Street Replacement Elementary School
Park Street Elementary School opened in 1942. With approval of the voters on the E-SPLOST V referendum, the current Park Street Elementary will be replaced with a new contemporary school building that honors the rich heritage and traditions of the Park Street Community.
Park Street Historical Architecture Presentation
This project is currently in progress
- Project Manager: Erick Hofstetter, Assistant Superintendent; Jimmy Pace, Director of Maintenance; Torey Bradley, Director of Technology and Informations Systems; MCS Operations team
- Architect: Breaux & Associates
- Contractor: R.K. Redding Construction
Completed Projects
-
A.L. Burruss Elementary School Renovations Project
A.L. Burruss Elementary School Renovations Project
Start Date:
March 27, 2017
Completion:
July 25, 2017Key Project Highlights
• New roof (replacement) • New carpet (classrooms, media center, offices) • New HVAC units (in each classroom) • New paint throughout • New ceiling throughout • New countertops/sinks in classrooms • New LED lighting throughout (interior/exterior) • New serving line (cafeteria) • New emergency generator • Electrical upgrade (Kitchen) • New fire alarm system • New LVT flooring (corridors, cafeteria) • New intercom system (telephone) • New ceramic tile in restroom • New door hardware (key system) • Automated controls (fixtures) in large restrooms • New water heaters throughout • New water coolers with “bottle fillers”
All HVAC and lighting will be connected to an energy management systemFront entrance and corridor will be modified to create a security vestibule for visitor control
A new canopy will be added to the front of the school providing a clear gateway to the main door, shelter from inclement weather, additional activity space, and building aesthetics. Guaranteed Maximum Price (GMP)
$4,224,238.35
Total Reimbursement
$1,356,683
Projected Cost
$2,867,555.35
ALB Renovations Progress Videos Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Day 11 Day 12
-
Synthetic Turf Field Project
This project installs synthetic turf at the "Soccer-Lacrosse Stadium" at Marietta High School. This multi-use field will host Soccer and Lacrosse games and is lined for football games as well as band competitions.
- Work timeline: October, 2018
- Completion Target – January 1st, 2019
- Contractor: Deluxe Athletics
Below is a rendering of the field layout:
Gallery
-
Gymnasium Floor Installation
This project installed hardwood maple floors in the gymnasiums of Hickory Hills Elementary, West Side Elementary, and Marietta Center for Advanced Academics. These gyms previously had carpeted floors; installing the hardwood floors at these schools meets the districts specification and continues the tradition and pride of all schools. All Work was during and completed during the month of November.
- Project Manager: Jimmy Pace, Director of Maintenance
- Contractor: Stevens Gymnasium, Inc.
Click picture below for a "fly-by" video of the recently installed gym floors:
-
MSGA Roof Replacement
This project includes the replacement of approximately 100,000 square feet of roof on the Marietta Sixth Grade Academy main building.
- Project Manager: Jimmy Pace, DIrector of Maintenance
- Architect: Breaux & Associates
- Contractor: R.K. Redding Construction
Tentative Dates:
- Project Start: June 2018
- Project Completion: August 2019
- Approximately 100,000 square feet
Gallery
Facilities Contacts
-
Chuck Gardner
Chief Operations Officer
250 Howard Street
Marietta, GA 30060
Phone: (770) 422-3500, ext. 7288Jimmy PaceMaintenance Director
250 Howard Street
Marietta, GA 30060
Phone: (770) 422-3500, ext. 7265Devlin BrewerExecutive Secretary
250 Howard Street
Marietta, GA 30060
Phone: (770) 422-3500, ext. 7257Vacant
Capital Projects/E-SPLOST Secretary
250 Howard Street
Marietta, GA 30060
Phone: (770) 422-3500, ext. 7218